How a Commercial job's contract gets from the Letter of Intent to an executed contract in PM: the contract tasks the Commercial P2 and P3 templates build, the Contract Status field, the Contract Review window with its AI review, and the flags each seat has to approve before the contract can be marked Approved/Received.
Current as of November 6, 2026. The contract, the findings and the people named … Example in the pictures are example data; the screens themselves are the real ones. Click any picture to see it full size.
New: Done reviewing, Remind those not done, and Contract Review in your daily digest
1The big picture
On a Commercial job the contract is reviewed and approved by the President and upper management, usually before a Project Manager is seated. PM keeps that work in four places that move together, so you only have to drive one of them and the others follow.
Field
Contract Status
To Do, In Review, Waiting on Customer, Approved/Received. On Settings → General Information, in the review window, and read-only on the Dashboard.
Tasks
Four contract tasks
Contract - Received, - Internal Review, - Clarification Sent to Customer and - Executed. Built by the Commercial template, and moved by the review.
Window
Contract Review
The uploaded contract, its AI review (risk, findings, obligations, watchlist), decisions on each finding, and the flags.
Gate
Required approvals
A clause flagged “Approval required” to a seat or reviewer must be approved by that person before Approved/Received can be chosen.
The short version. Upload the contract: from Settings → General Information (the signature icon beside Contract Status), the Upload the contract button on any contract task or on the Dashboard, or simply by attaching the PDF to Contract - Received and saving. PM marks Contract - Received Done, starts Contract - Internal Review, sets the status to In Review and runs the AI review. Reviewers walk the findings and flag what needs a decision. When every required approval is in, set Contract Status to Approved/Received: Internal Review and Executed close, and the contract's obligations can become the job's tasks.
2The template's contract tasks
Commercial P2 (Plant 2, Ohio City) and Commercial P3 (Plant 3, Lexington) carry the same contract chain. LOI Received and the four contract tasks are assigned to the President role, and each task's dates are tied to the task before it, so marking a step Done moves the rest of the chain.
LOI ReceivedThe start of the chain. The HubSpot Crawler marks it Done on the day HubSpot says the deal entered LOI Received (or a later stage), and the chain re-dates from there.
President · no date link
Contract - ReceivedStarts when LOI Received is Done; due 14 calendar days later. Uploading the contract marks it Done.
LOI Done → +14 days
Contract - Internal ReviewThe review itself. Uploading starts it, flags land on it as checklist items, and it closes at Waiting on Customer or Approved/Received.
+5 business days
Contract - Clarification Sent to CustomerCloses when the Contract Status is set to Waiting on Customer.
+1 business day
Contract - ExecutedCloses when the Contract Status is set to Approved/Received.
+3 business days
Assign Project Management TeamThe hand-off to the job team (Commercial Project Manager), then Schedule Pulled for the Project Manager.
+1 business day
New projects start with Contract Status To Do, whether they are built from the template, copied, imported or created by the HubSpot Crawler (Other/Misc projects are left blank). Older jobs that predate the field stay blank, which means “not tracked”.
No contract tasks on an older job? The review creates any contract task the project lacks the first time it needs it, copying the assignee, collaborators and watchers from the project's own template (else a template of the same project type, else any template).
3Contract Status
The field sits in Settings → General Information, beside the Contract Number. It saves the moment you pick a value; it does not wait for the Settings tab's Save. Anyone who can edit the project can change it; people who can only view the project see it disabled.
The signature icon beside the label opens Contract Review (or the upload, if no contract is in yet). While approvals are open, the red line under the field says who the contract is waiting on.
Status
When it is set
What PM does to the contract tasks
To Do
Automatically on every new project.
Nothing.
In Review
Automatically when the first contract is uploaded (from blank or To Do), and when a revised contract is uploaded while Waiting on Customer. Can also be set by hand.
Internal Review moves from To Do to In Progress.
Waiting on Customer
By hand, when the clarifications go to the customer.
Internal Review and Clarification Sent to Customer are marked Done, with a note naming who set it.
Approved/Received
By hand, and only when no required approval is open (see section 8).
Internal Review and Executed are marked Done. Set from the review window, it also offers to create the obligation tasks.
Every change is written to the project's History, marked “(Contract Review)” when PM made it automatically.
4Uploading the contract
There are four ways in, and they all do the same thing: the PDF is saved to the project's Attachments tab, Contract - Received is marked Done, Internal Review starts, Contract Status becomes In Review and the AI review runs. The file must be a PDF of 15 MB or less. Anyone who can edit the project can upload; people who can only view it see the buttons disabled, with the reason.
1 · The signature icon in Settings
Settings → General Information, beside the Contract Status label (picture in section 3). Once a contract is in, the same icon opens the review instead.
2 · The banner on a contract task
Until a contract is in, every contract task's banner offers Upload the contract. From the Edit window it first saves the task through its usual checks (so nothing you typed is lost, and the review's own updates to the task are not saved over), then opens the upload. From the View window it opens the upload straight away. Once a contract is in, the button reads Open Contract Review.
3 · The Dashboard
Dashboard → Project Information shows Upload the contract under Contract Status while none is in.
4 · Attach the PDF to Contract - Received
Attach the contract to the Contract - Received task as you would any file and save the task. PM then asks whether to send it to Contract Review:
Send to Contract Review uploads that attachment and opens the review window. No, keep it on the task leaves it as an ordinary task attachment. The file stays on the task either way, and a note on the task records which file was sent.
Only Contract - Received asks. PDFs attached to the other contract tasks are treated as ordinary attachments (markups, letters).
Only PDFs are offered. A photo or a spreadsheet attached in the same save is ignored.
Several PDFs in one save: you pick which one is the contract.
Once a contract has been reviewed, a new PDF on Contract - Received is offered as a revised contract: it gets its own AI review, the existing flags are re-checked against it, and a Contract Status of Waiting on Customer goes back to In Review.
Two PDFs in one save.A new PDF after a review exists.
Help is one click away. A ? beside the Contract Status label, on the contract task banner and on the Dashboard row, and the Help button in the review window's title bar, all open this guide.
5Step by step
LOI comes in. LOI Received is marked Done (by the HubSpot Crawler, or by hand). Contract - Received now has its due date.
Upload the contract. Any of the four ways in section 4: the signature icon in Settings, Upload the contract on a contract task or the Dashboard, or attaching the PDF to Contract - Received. It must be a PDF of 15 MB or less; compress a larger one in Acrobat (Reduce File Size). The file is saved to the project's Attachments tab and the Contract Review window opens.
PM takes the first steps for you. Contract - Received is marked Done with a note, Contract - Internal Review goes In Progress, and Contract Status becomes In Review. The AI review takes a few minutes; you can close the window, and a note lands on Internal Review when it finishes (risk rating, number of findings, high-risk count, obligations, watchlist terms not addressed).
Check the reviewers. A Commercial contract arrives with its default reviewers already listed (section 6). The President, or whoever owns Contract - Received, removes anyone who does not need to read this one and adds anyone missing.
Notify them. When the list is right, the owner of Contract - Internal Review clicks Notify reviewers: one email to all of them with a link to the review, copied to the owner.
Walk the findings. For each finding, read the clause, why it matters to us as the subcontractor, the suggested language and the question to ask. Then Mark reviewed, Mark acceptable risk (with a reason), or Flag to a reviewer or role.
Flag what needs a decision. A flag is either an FYI (acknowledge only) or Approval required, which blocks Approved/Received until it is approved. Each flag adds a checklist item to Internal Review and emails the people it is addressed to.
The people flagged answer. Each opens the review from the email, the task or the Dashboard, and clicks Approve or Acknowledge on their flag. Their checklist item on Internal Review ticks itself.
Every reviewer marks Done reviewing. When you have read the contract and answered any flag addressed to you, click Done reviewing in the review window, with a comment if you have one ("No concerns" is fine). Your name gets a ✓ and the time, and the owner of Internal Review is told (section 6).
Answer flags in Contract Review, not on the task. The flag items on Internal Review's checklist are read-only: each has an Answer in Contract Review link, and only answering the flag ticks it. Internal Review can't be marked Done while any required approval is still open; it closes on its own when the Contract Status moves to Waiting on Customer or Approved/Received.
Send clarifications if needed. Set Contract Status to Waiting on Customer. When the customer sends a revised contract, use Upload revised contract: the status goes back to In Review, the new revision is reviewed, and every existing flag is re-checked against the new text.
Approve. When the lock line reads “No required approvals outstanding”, set Contract Status to Approved/Received, preferably in the review window. Internal Review and Executed close, and the window offers to turn the contract's obligations into tasks.
Hand off. Assign Project Management Team is next in the chain. Obligation tasks wait on the Project Manager role and move to the PM as soon as that seat is filled.
6Reviewers
The reviewers are the people who read this contract. Each can be flagged by name, collaborates on Contract - Internal Review, and is added to the project team if they were not on it.
Each reviewer shows the role that put them there. The green envelope means they have been notified about this contract; hover a name for when. A line underneath lists any default seat that could not be filled.
The default reviewers
When the first contract is uploaded on a Commercial project, PM adds these seats' holders:
Always
Also when MBI installs the job
CEO · COO · President · Business Development · Estimator · Detailer · Commercial Project Manager · Finance Director
VP of Field Operations · Director of Safety and Field Strategy · Installation Relationship Manager
Who fills each seat: the person in that role on the project. An empty seat goes to the role it rolls up to; failing that, to the person in that role on the project's template (Commercial P2 or P3). That last step is how the CEO and COO reach older jobs, which were built before those seats were added to the templates.
Not added: a seat nobody holds, or one held by someone no longer in the company directory. The Reviewers row lists these with the reason, so the President can add the right person by hand.
Once only. The defaults are added at the first upload. Answering MBI Installs This Project later, or uploading a revised contract, does not add or remove anyone, and a reviewer the President removed stays removed.
Reviews already under way on November 6, 2026 (not yet Approved/Received) were given the defaults the same way, keeping everyone already listed.
Who changes the list
The project's President, the owner of Contract - Received, or an administrator can add or remove reviewers. Everyone else sees the box disabled, with the reason. Removing a reviewer who still has an open flag leaves that flag for an administrator to answer.
Done reviewing
A reviewer with nothing flagged to them still says they have read the contract. In the review window, click Done reviewing beside the Reviewers row. Add a comment if you have one; it is optional.
Done reviewers turn green with a ✓ and the time; the count beside Reviewers says how many of them are done. Hover a name for the comment and, if someone marked it for them, who.The comment goes into the note on Contract - Internal Review, which @mentions its owner.
Answer your flags first. While a flag addressed to you is open, the button is off and says how many are left.
A new flag reopens your review. If someone flags something to you after you were done, you get the usual @mention note, and your ✓ clears until you answer it.
A revised contract starts everyone over. After Upload revised contract, every reviewer marks Done reviewing again for the new version.
On someone's behalf. An administrator, a project admin or the owner of Contract - Internal Review can mark a reviewer done, for example after a phone call, with the ✓ beside their name; it shows as marked by them. The same people, or the reviewer, can undo it.
Remind those not done. The owner of Internal Review (or an administrator) can send one reminder email to only the reviewers who have not finished, copied to the sender.
With a flag still waiting on you, Done reviewing stays off until you answer it.
Notify reviewers
Adding someone does not email them. Once the list is set, the owner of Contract - Internal Review (or an administrator) clicks Notify reviewers. One email goes to every reviewer not yet notified, with the risk rating, the number of findings and a link to the review. The owner is copied, and so is the sender.
The button names who will get it before anything is sent.
Nobody gets it twice for the same contract. After a send the button turns off. Adding a reviewer turns it back on, and the next send goes only to the new people.
A revised contract starts a new round. After Upload revised contract, the button offers everyone again, so all reviewers hear about the new version.
When it is off, hover it for why: you are not the owner of Internal Review, there is no contract or no reviewer yet, or everyone has already been notified.
A note on Internal Review records who was emailed and when.
7The review window
Open it from the signature icon in Settings, the Review button on the Dashboard, or Open Contract Review on the banner of any contract task, once a contract has been uploaded. It opens in its own browser tab, with a Help button in its title bar.
The review window's title bar: Help opens this guide; Project Manager goes back to the project.The header: the contract file, its revisions (a picker appears once there is more than one), the AI's risk rating to us as the subcontractor, Contract Status with its lock line, and the buttons. Open the contract shows the PDF with the flags beside it; Save report to Attachments writes the review as a PDF to the project's Attachments; Re-run analysis reads the contract again and keeps every decision and flag.Under the header: how much of the review has been walked, the counts (findings, high risk, accepted, open, obligations, open flags), the AI's summary, then one card per finding. Filter the findings by open, not yet reviewed, risk level or category. Assigned lists everyone the finding has been flagged to: orange with a flag while their answer is open, green with a check once they have answered.
What each finding offers
Show in contract opens the PDF at that clause.
Mark reviewed records that someone has read it (Undo reviewed takes it back).
Mark acceptable risk asks why, and records the decision with your name in the company-wide acceptance ledger. A later contract with a near-identical clause shows it as accepted, inherited from an earlier contract; a merely similar clause is shown as a suggestion to compare, and someone has to accept it there. An acceptance can be withdrawn with a reason; the history keeps both.
Flag to a reviewer or role opens the contract at the clause, ready to flag it (section 8).
Further down: What we are responsible for (the obligations, section 9), the Watchlist of terms the review looks for in every contract, marked present or not addressed (confirm those with the customer), and Questions for legal / exec review.
8Flags and approvals
To flag a clause, open the contract and drag a box around it, then click Flag something (or start from a finding's Flag to a reviewer or role). Choose the kind and who it is for. A flag needs readable text under it: on a scanned page, upload an OCR'd copy first.
Addressed to
Who can answer
PM/PE
Whoever holds the project's Project Manager or Project Engineer seat.
Field Superintendent
The Field Superintendent seat holder.
Finance (AR)
The Accounts Receivable seat holder.
Safety
The Director of Safety and Field Strategy (or Safety) seat holder.
A named reviewer
That person, while they are on the contract's reviewer list.
An empty seat is answered by the holder of the role it rolls up to, named as such (never the Project Lead). With nobody there either, only an administrator can answer it, recorded as answering on the seat's behalf. Better: fill the seat on the project's Settings tab (Roles).
An administrator can answer any flag; the record says it was an administrator, on whose behalf.
Removing a flag is open to the person who raised it, or an administrator. It stops blocking, and the record of it is kept.
The same Assigned names appear beside the contract, in the viewer's Review findings list down the left side. They come from flags raised on that finding, or on the same contract section.Each flag becomes a checklist item on Contract - Internal Review, and ticks itself when it is answered. The people it is addressed to are added as collaborators and @mentioned in a note.
The Approved/Received lock
Approved/Received can be chosen only when no Approval required flag is open. FYIs never block. While approvals are open, the lock line in Settings and in the window names who the contract is waiting on, and trying anyway shows exactly what is outstanding:
The status stays where it was. Each line is a seat, who holds it, and the contract section.
9Obligations
Findings are the risks to decide on; obligations are what we must do once the contract is signed (submittals, insurance certificates, closeout documents), each with its section and when it is due.
One obligation at a time can become a task with Create task. Create tasks for all unlocks once the Contract Status is Approved/Received, and the review window offers it the moment you approve there.
Obligation tasks are titled “Contract obligation: …”, carry the clause and its timing in the description, and are assigned through the Project Manager role. Until a PM is seated the project lead stands in, and the tasks move to the PM as soon as the seat is filled.
10Finding your part
People asked to approve a clause usually cannot open the Settings tab, so the review is reachable from three other places:
Dashboard → Project Information. Contract opens the current PDF; Review opens the window, highlighted with a count when something is waiting on you: open flags addressed to your seat, plus open contract tasks you are assigned to or collaborating on.Every contract task, and every obligation task, carries this banner in its View and Edit windows. Before a contract is in, the button reads Upload the contract instead (section 4).
And the emails: the Notify reviewers email links straight to the review (section 6), and a new flag addressed to you sends the @mention note from Contract - Internal Review, with a link to the task. Those notes point you to the project's Dashboard → Project Information → Contract Status → Review.
Your daily digest
Until you mark Done reviewing, your daily Project Manager digest has a Contract Review section: each project with its Contract - Internal Review start and due dates, a link to the review, a line asking you to review the contract, and every open flag addressed to you. The owner of Internal Review also sees how many reviewers are done. It appears whatever the project's status, and stops once the contract is Approved/Received or Internal Review is Done, Cancelled or deleted (it comes back if the task is reopened). The Dashboard's Review button also counts your review as waiting on you, and the Contract Status row shows how many reviewers are done.
11Good to know
The AI review is a first read, not a decision. It reads the contract from our side as the subcontractor. If it cannot run, the window says so and nothing is invented; use Re-run analysis once the cause is fixed. A run cut short by a service restart shows as interrupted and can be re-run the same way.
Revisions keep the history. Each upload is a revision; the picker in the header shows earlier ones. Flags carry over, and a flag whose clause is gone from the new text is called out in a note on Internal Review.
A file attached to a task is not the reviewed contract until it is sent. Only an upload (any of the ways in section 4) starts a review; on Contract - Received, PM asks when you save.
Templates have no Contract Review. The icon is disabled while editing a template, and on a new project until it has been saved once.
View-only access lets you read the review and the contract, but not upload, decide, flag or change the status.
HubSpot. From the Contract Received - Active stage on, PM is the record for the deal and HubSpot follows PM, not the other way round.
Checklist for the President's office. LOI Received Done · contract uploaded · reviewers checked · reviewers notified · every finding reviewed or accepted · every required approval answered · Contract Status Approved/Received · obligation tasks created · Assign Project Management Team.