MBI Project Manager · System overview for new users
Projects, tasks, and how the work stays in sync. An overview for anyone new to Project Manager, from the first login to working a job day to day: what a project and a task are, how to find your own work across every job, what each project tab does, how Commercial and Red Cedar jobs arrive and keep themselves current from HubSpot, SupplyPro, cERP and the Delivery Planner, and where the daily digest and the reports fit. Application administration is left out on purpose.
Kept current as the application changes
Everything in Project Manager hangs off a project: a named container with members, dates, settings and a list of tasks. There are two kinds, and they behave the same way.
A project's category and type (Commercial · Multifamily, Student Housing, Senior Living; Built-to-Rent · Red Cedar; Other) decides which template built it, which tabs show, and which filters and reports it appears in.
A task is the unit of work: something one person is responsible for finishing by a date. Tasks carry a title, a status (each project configures its own list, with To Do, In Progress and Done the usual spine), a priority, a type (General Task, Delivery, Shop Order, Purchase Order, Install, Email, Call, Meeting and more), start and due dates, a percent complete, a flag with a reminder date, tags, a checklist, notes, attachments, blockers (tasks that must finish first) and any custom fields the project defines.

Show less / Show more at the top of the task window switches between the everyday fields (title, status, priority, type, assignee, dates, description, checklist, attachments, watchers and notes) and every field. The View Task window has the same switch, and PM remembers your choice for both.
The one person responsible. Shows on your My tasks view, gets the assignment email when the task is due within 14 days (otherwise it waits for the digest), and gets the daily digest when it is late or coming up.
People working the task with the assignee. They can edit the task but not reassign it, they are added as watchers automatically, and they receive the daily digest for it. Use this for the second pair of hands.
People who need to know, not do. They are told about changes to the task and see it in their digest, with no edit rights implied. External email addresses can watch too, through the project's External Users list.
Relative dates let a task follow another: start when the frames are received, due three business days after the delivery, or keyed to the project's First Delivery or End Date. Template-built tasks arrive with these links in place, which is why a job's schedule moves together when a date changes.
Checklist items can link to tasks. In the Edit Task window, the link icon beside a checklist item’s trash can saves the task (with all its usual checks), then lets you pick another task on the project or create one; a new task’s title starts as the item’s text. The item then shows that task’s status, a Late, Due today or Upcoming flag, and who linked it. It ticks itself when the linked task reaches Done and unticks if the task is reopened, whatever moved it (a person, a cERP or SupplyPro sync). Ticking it by hand moves the linked task to Done through the same prompts as moving its card. The swap icon re-links the item to a different task, and the broken-link icon removes the link on Save. The linked task shows Checklist item on: with a link back, and task cards show a small link icon when any item is linked.

Custom fields are defined per project in Settings and show on every task of that project (a release number, a plant code, a sign-off). They can be filtered and exported like any other field. Two fields are built in and belong to one task type each: Opening appears on Punch tasks, and MBI Shipment appears on Delivery tasks, where the shipment number leads the task title and shows on the card and in the description.

The starting screen shows the same data two ways. Switch with Dashboard View / List View at the top left; PM remembers your choice.

In the Projects tile, a count opens the list of projects in that status. A project whose name shows in green has a Comsense number entered; on the List View, the same projects' cards carry a light green tint.

The filter bar at the top of Home applies to everything below it. Open the panel with the chevron at the right end to build a filter from project fields (category, status, plant, type) and task fields (status, type, assignee, due window, tags). Save current names it; Make default makes it the view you land on. After you change filters, Reset filters in the bar puts your default saved filter back exactly as saved, while Clear all filters empties everything. A saved filter also remembers the quick toggles in the bar (Assigned to me, My team, Favorites only and, for application administrators, Show restricted) and sets them when you pick it. Saved filters here span every project you can see, which is how you get one true picture of your workload rather than one project at a time.


Recent Projects lists the last eight projects you opened (PM keeps thirty) so you can jump back without searching. The search box beside it finds tasks by title.

Open any project and the tabs run across the top. Estimating, Detailing and Fulfillment are the cERP-side tabs; Fulfillment gets its own section below.
Settings is the project's record and its permissions. The sections open one at a time: General Information (name, status, deal stage, dates, plant, type, HubSpot deal, contract number, unit count), Project Location, Developer, Architect, General Contractor, Install (whether MBI installs, whether full-time ND&T site supervision is required, which installers, mobilization dates), Financials (billing and retainage terms, and the payment method: Check, ACH or Other with a note), Project Tags, Task Statuses, Custom Task Fields, Task Types & Notifications, Assigned Users, Roles and External Users. External Users lists people outside the company: anyone watching a task, plus people added there directly with Add, often only so they receive the Delivery Planner's 3, 2 and 1 week delivery notices. Each has a Delivery notifications switch.

Who can see and do what. Only Assigned Users can open a project. Roles (Project Manager, Project Engineer, Field Superintendent, Estimator, Business Development, Commercial Project Manager and others) name who holds each seat; template tasks are assigned to the role holder, so changing a holder moves their open tasks. When someone leaves or changes jobs, an administrator hands their work to a replacement in one step (Application Settings → Hand Off Work): every seat, lead role and open task they hold on open projects moves, split between people by project or by task if needed. The new person gets one email listing what they took over, not an invitation per project, each project's History records it, and closed tasks and finished projects keep the original name. A role nobody holds rolls up: each role in the Roles section has a Rolls up to picker, and an empty seat's tasks go to whoever holds that role instead of the Project Lead. On Commercial jobs (since November 4, 2026) the Field Superintendent rolls up to the VP of Field Operations, the Project Manager and Project Engineer to the Commercial Project Manager, and the Detailer, D10 Estimator and Estimator to the Preconstruction Manager. If that seat is empty too, the work keeps climbing that role's own rollup, and only then goes to the lead. Pickers read "Field Superintendent — unassigned → Karli Turnwald (VP of Field Operations)" so you can see where it lands. The person a seat rolls up to sees it on the project's Dashboard under Roles rolling up to you, with a picker to assign someone; they need no Project Admin rights for that. The new holder gets one email listing the open tasks that moved to them, and the daily digest reminds the parent holder of seats still rolling up to them. Templates carry their rollups onto the projects built from them, and an administrator sets the company default for each role under Application Settings → Project Roles. Several people in one role: a role an administrator marks Allow several holders (Application Settings → Project Roles) can be held by more than one person on a project, for example two Project Engineers on a large job. Its row in the Roles section gets an + Add another picker. The first person is the Primary: tasks assigned to the role go to them, and HubSpot shows their name. The other holders are added to those tasks as collaborators. They also get everything the role grants: its permissions, its Contract Review approvals (either holder can approve), its emails and its report columns. The arrow button next to a holder makes them the Primary. When a template's additional holders change, Apply template changes to projects lists each person added or taken off. An added person joins the role next to whoever the project already has, and becomes the Primary if the role is empty. A removal never takes off a project's Primary. Project Admins and the project lead can change Settings; other members work the tasks. Restricted categories hide financial detail from people outside the allowed departments. Application administrators can change anything and are the only ones who can remove tags a template applied.

Changing a template. Application administrators edit templates under Templates. Saving one that has projects built from it opens Apply template changes to projects, which lists exactly what that save changed: a renamed status, a person added, a role's new holder, a permission switched on. Untick any change to keep it on the template only, and pick the projects. Each project shows how many of the changes reach it, and why the others don't (for example, the project already put someone else in that role). Only those changes are pushed; nothing else on the project is touched. Template tasks and per-project fields like dates and the lead are listed but never pushed: they shape new projects only.

The project Dashboard opens with Project Information (contract, HubSpot, plant, type, unit count, lead, PM, PE, superintendent, installers, developer, architect, GC), then the same overview tiles as Home scoped to this job, completion by task type, the material shipped, freight and delivery widgets, and the late, upcoming and recently completed lists.

In Project Information, the Estimator, D10 Estimator, Detailer and Detailing Tech rows have a pencil. Click it and pick a person (the Preconstruction department is listed first) to fill or change the role; the person joins the project if needed, and the role's open tasks move to them. The pencil shows for application administrators, the project lead and Project Admins, and for the Preconstruction Manager on projects where the role rolls up to that seat.
On both Dashboards, Material Shipped, Billing Progress and Freight open collapsed, the same way Project Information and Financial Information do. Click a header (or press Enter on it) to expand it: its figures are read from cERP only then, so the Dashboard itself opens quickly. On a project, a widget you collapse again keeps its headline figure in the header, such as 12.3% shipped, and all three close again the next time you open a project. On Home they stay the way you left them until you reload the app. Inside the project’s Freight widget, the Delivery route section opens folded too: click its heading to see the route, and fold it again to keep just the miles and drive time. It shows the distance and drive time from the plant to the site; each delivery's pickup date and time are worked out from that by the Delivery Planner.
The Material Shipped widget answers “how much of this job’s material has gone to site?” as a percentage, and shows where the rest stands: on a sales order, on a release with no sales order yet, or on no release at all. Switch the measure between Planned cost (each piece weighed by its planned cost in cERP), Pieces and Openings; the planned-cost view shows shares only, never an amount. A red flag counts sales orders past their shipment date and releases past their due date. On Home the same widget lists every project you can see, one bar per job, and for Comsense jobs counts the shipments delivered. Comsense jobs carry a green Comsense mark on this widget and on Billing Progress.

On the project Dashboard, Opening Lookup, Delivery Schedule and Pending Change Requests open collapsed too. A closed Delivery Schedule or Pending Change Requests header still shows its count (for example “24 open”), and when open its count link and Excel button work as before. A job supplied through Comsense carries a Comsense badge on the Opening Lookup, Material Shipped, Billing Progress and Freight headers.
The Opening Lookup widget sits above Material Shipped on the project Dashboard and answers “where does this opening stand?” Expand it, type an opening number, a unit (for example 112) or a location, and pick the opening from the list; each match already shows how much of it has shipped. The widget then gives the headline: pieces shipped, what is on a sales order, on a release or on no release, the next ship or due date, and how many releases, sales orders, shop orders, purchase orders, receipts, shipments and delivery tasks sit behind it. Full details opens a window with every one of those listed, each with a link to its cERP page and its PM task, a link to the opening’s Complete Opening Detail, and an Excel export. The same window opens from the chart icon beside an opening on Fulfillment → Openings. It reads what PM last pulled from cERP and shows no dollar figures; a quantity marked “shared” is the whole order line’s, covering every opening on it.
Punch items are things on an opening that still have to be put right. On Fulfillment, Openings every opening carries the Punch task type’s icon: in the type’s color while any item is open, green once every item is complete, faint when there are none. Click it to list the opening’s items, tick them complete, set each one’s category and who is responsible (MBI unless you say otherwise), and add more, one per line. Expanding an opening shows a Punch pill beside Items/Mat’l with the same items and a link to the task; the Punch column filters the page to openings with open items. Each opening with punch work has one Punch task named for the opening, and every item is a checklist line on it. The Field Superintendent owns the task on an install job, with the Project Manager and Project Engineer as collaborators; on any other job the Project Manager owns it, with the Project Engineer. Each item can carry photos and files: the camera button on an item (or Photos / files beside Add, for the item you are typing) attaches them, pictures show small in the list, and they are kept as attachments on the Punch task, so they also appear on the task and on the project’s Attachments tab. You can also start from the task side: create a task of type Punch and fill in its Opening. Upload punch list above the Openings table takes an .xlsx or .csv with Opening and Punch item columns (Category, Responsible, Status and ID are optional), shows what it will add and which rows it will skip, and leaves alone anything already on the list; Punch list exports every item, or a blank sheet to fill in when there are none. The project Dashboard’s Punch widget, collapsed like its neighbors, counts open and complete items and lists the openings with the most open punch, and the Opening Lookup window has a Punch section. An item counts as complete when its line is ticked or its task is closed. Adding items emails nobody; the tasks show in their owners’ lists and the daily digest.
Click any row to drill down. Shipped lists each posted shipment with its date, shipment number, sales order and release; On a sales order lists the open orders with their shipment and requested delivery dates; On a release lists the releases with their due dates; Not on a release groups what is left by item category. Open a line to see its items, the openings they belong to and the pieces, and use Export CSV to take the list to Excel. Every item line of the cERP material list counts; internal change orders and change orders still in Planning are left out.

The Billing Progress widget sits under Material Shipped and splits the contract into four parts: Paid, Invoiced, not paid, Shipped, not invoiced (material that has gone to site and can be billed) and Remaining. The contract is the base contract plus its approved change orders; on the project Dashboard switch between With change orders and Base contract only. Change orders not approved yet are left out and listed. Everyone who can open the project sees percentages; dollar amounts are added for the project’s members and billing roles and for people who can open the Commercial Revenue Forecast. Click a row for the invoices (with what is still open on each), the billing lines shipped ahead of invoicing, or the change orders, each with Export CSV. On Home the widget lists every project you can see. Jobs billed in Comsense follow the latest Orders Analysis import, as the Revenue Forecast does; their contract already includes change orders, and Shipped, not invoiced is not known for them.

The Freight widget (on the project Dashboard, and summed over your projects on Home) counts the job’s cERP shipping by delivery method, with what is invoiced and what remains. Switch it between Shipments (one per sales order, the way Logistics works its tasks) and Deliveries (trips: the shipments going to the same jobsite on the same date by the same shipment method). Contract jobs price their sales orders at zero in cERP, so each line is valued at its own cERP price when it has one and otherwise at the material list’s unit price for the same item; a warning says when a job’s material list carries almost no price.

The Tasks tab is a board, one column per status. Each card shows type, priority, due date, late or upcoming marks, progress and the assignee. Drag a card to another column to change its status. PM first asks Move this task? and shows the task, its old and new status, due date and assignee, so you can cancel if you grabbed the wrong card. The percent-complete questions that may follow also have Cancel move. After the move, an Undo button shows for a few seconds and puts the task back, along with any linked dates the move shifted. The arrow buttons on a card move it without asking. Click a card to open the task window, or use Add Task to create one. The filter bar at the top of the tab works like Home's, with one difference: a filter saved here belongs to this project. Save a Home filter for cross-project views and a project filter for the slices of one job you return to.


The Calendar tab places the same tasks on time: Timeline (a Gantt-style strip with zoom), Day, Week, 4 Weeks, Month and Year, with a Weekends toggle and a List alternative. The project filters apply here too.

Attachments holds the project's files and every file attached to a task, with upload, open and a link to the project's Teams library.
A project built from a template starts with the template's files. The Commercial templates carry the fillable Logistics Sheet.pdf: PM writes the project's name at the top of each project's copy, and writes it again when the project is renamed and saved in Settings. What you have typed into the rest of the form stays.

Nobody creates a Commercial project by hand. The HubSpot Crawler runs every weekday at 7:15 and reads the deal pipeline:
The template's tasks carry the TemplateTask tag, and the install-only ones carry TemplateInstall: switching MBI Installs This Project on or off adds or removes those tasks (finished ones stay). The Template tasks quick filter keys off that tag.
Any member can also open the Sync with HubSpot window from Settings → General Information to compare the project with its deal field by field and push or pull individual values.

The template's contract chain (LOI Received, then Contract - Received, Internal Review, Clarification Sent to Customer and Executed, all on the President role) is driven by Contract Status and the Contract Review window. Upload the contract PDF from the signature icon beside Contract Status (Settings → General Information), the Upload the contract button on a contract task's banner or on the Dashboard, or by attaching it to Contract - Received and saving, which asks whether to send it to review. PM then runs an AI review of the contract from the subcontractor's side and lists the default reviewers: the CEO, COO, President, Business Development, Estimator, Detailer, Commercial Project Manager and Finance Director, plus the field leadership when MBI installs the job. The President or the owner of Contract - Received adjusts that list, and the owner of Contract - Internal Review emails everyone at once with Notify reviewers. Clauses are flagged to the PM/PE, Field Superintendent, Finance (AR) and Safety seats or to a reviewer by name, each finding shows who it is assigned to, and Contract Status cannot reach Approved/Received while a required approval is open. The ? beside each of those buttons, and Help in the review window, open the Contract Approval guide.
The Commercial templates carry a Send Logistics Sheet task, owned by Business Development and dated from the Kickoff Meeting. It asks the General Contractor for what the trucks need: the delivery address and receiving hours, site access and unloading, and who to call on site. The Delivery Planner keeps one online form per project. Open the task and its banner says where the sheet stands (not asked yet, waiting, or filled in, when and by whom, and what is still missing). Send Logistics Sheet opens the email: pick the General Contractor's contacts already on the project or type a name and address, add a CC if you like, and change the message if you need to. The form link is added under your message and cannot be edited. The email goes out from your own mailbox, so replies come back to you, and the task then moves to Done at 100%.
The General Contractor fills the form in once, with no sign-in, and the finished PDF appears on the project's Attachments by itself. A name and address you typed is saved to the project's General Contractor contacts for next time. Send again re-sends the same link while it is still waiting; once the form has been submitted the button reads Send a new link, which makes a fresh form for an update. The task's assignee and collaborators, the project lead, Project Admins and application administrators can send; everyone else sees the status with the button disabled. It works before the job has a cERP contract number. Administrators set the standard wording under Application Settings → Delivery.
Red Cedar Homes schedules its subdivisions in SupplyPro, and PM mirrors that. Each Red Cedar job is a project (University Commons, Holly Grove, Towns at Bisaner) and each lot's work arrives as tasks: Deliver Interior Door / Trim Material, Install Vinyl Plank Flooring, Deliver Shoe Mold, Cabinet Touch Up, numbered by lot. A Future Orders status holds what SupplyPro has released but not yet scheduled.

cerpoutofsync is one whose date could not be pushed to its sales order.
For jobs linked to a cERP contract, PM creates and maintains tasks from cERP documents, so purchasing and logistics work appears without anyone typing it:
| Task type | Made from | Who gets it, when it is due |
|---|---|---|
| Delivery | Sales orders and their shipments (and, for Red Cedar, SupplyPro) | Logistics; start and due on the order's Shipment Date |
| Shop Order | Open shop orders in cERP, with their lines and openings | The plant; due on the shop order's dates |
| Purchase Order | Open purchase orders, one task per buyer (Purchaser Code) | Purchasing; due on the Promised Receipt Date |
| Release | Each cERP release on the contract | The project's role holders; one PM-owned task per release, kept even when Done |
Pickup details on delivery tasks. The Delivery Planner works out when each load has to leave the plant: the pickup date and time, from the delivery date and time and the drive time stored for the project, with its own per-truck rules (a GLM same-day run, a planner's override). PM reads those on every hourly, nightly and manual pull and puts them at the top of each delivery task's Description, one line per order: pickup date and time, delivery date and time, transit days and the truck. An open delivery's card on the Tasks board shows the pickup under its due date, and Fulfillment → Deliveries has Pickup Date, Pickup Time and Truck columns. When the Delivery Planner has no pickup date the line says why, and once a delivery has shipped the task keeps the last details it had. The task's own Start and Due dates stay on the delivery date.
These tasks re-sync from cERP every hour, and completing the underlying document completes the task. Some dates can be changed from PM and written back: a release's due date (its lines on the same date move with it), a sales order's dates (PM asks first), a purchase order's promised receipt date and a shop order's dates. The task window says, under the date, what a change will do in cERP.
Fulfillment is PM's window onto cERP for one contract. Every page is a table with the same tools: a filter row, ⓘ on each heading explaining the column and naming the cERP field behind it, totals, column choices and a sort you can save as a view per table (the Columns panel opens over the page, so its whole list and the Save button are always in reach), the first column (Opening, Release, Order #; Actions and MPO # on Manual Purchase Orders) pinned at the left while the table scrolls sideways, an Excel export, and the All change orders switch to narrow to one change order.
How current it is. "Data as of" at the top right is the oldest pull among the cERP data that page reads, so it holds for every column. A full pull runs every night. An automatic pull at :35 each hour refreshes sales orders, shipments, releases, shop orders, purchase orders and receipts, the assignments on any release that changed, and the Billing data on projects whose Billing page was used in the last 7 days; when that has moved part of a page since the nightly pull, the label adds "hourly data through" and the time. Hover the label to see each dataset with its own time and how often it is pulled. Refresh project (or Pull from cERP) pulls now, and warns when a slow dataset will take a while. Nothing on these pages is typed in PM: fix the source document in cERP and pull.

The Openings table also shows each opening’s Area, and the pencil beside an opening’s mark changes the opening in cERP: hand, heading, type, interior or exterior, building, floor, area, locations, door and frame types and sizes, jamb anchors and keying. The window reads the opening from cERP when it opens and saves only what you change. Each box offers the values already used on the job, so repeated entries such as Area are a pick rather than typing; a Heading must already exist on the contract’s heading list in cERP. The Project Manager, Project Engineer and Commercial Project Manager on the project, and application administrators, can use it; for everyone else the pencil is shown disabled with the reason.

The releases on the contract: description, phase, due date, status, line count and how many lines are not yet on a sales order. The Sales Orders and Purchase Orders columns name every order carrying the release's material: blue is open, amber is partly shipped or received, and green with a ✓ is finished. Finished orders still show, even though cERP deletes a sales order once it has shipped and posted in full; PM rebuilds them from their shipments and receipts. Orders are matched by the release number on their lines. The ⚠ on the Sales Orders heading narrows the list to releases with no sales order yet. Open a release to see its lines, and use its Sales Orders, Shipments and Purchase Orders pills for the detail. The Sales Orders, Shipments and Purchase Orders subpages each have a Release(s) column, and an opening's Sales Orders pill lists its finished orders too. From here you create a release, put openings and material on one, move them between releases or take them off, and arrange the rows (order, groups, colors, hidden releases) for everyone on the project. The question mark beside the section title opens a full guide to these actions.

To decide exactly what goes on a release, use the release editor: the pencil beside a release number, Choose items… in the New release window, the Release editor button, or — on the Openings and Material pages — tick rows and click the filter button beside ⇄ to open the editor on just those rows. Filter by change order, phase, building, floor, opening, item category, product group, door / frame / hardware or item, several at once; each filter only offers what the others leave. Inside a filter, tick one choice, then Shift-tick another to tick everything between them. Then move rows between the Not on this release and On Release N lists with Add, Add All, Remove and Remove All, using click, Ctrl-click and Shift-click to highlight. Lines already on another release stay hidden until you ask for them, and moving one is marked on its row and confirmed before saving. The ? beside the Release Schedule heading opens the full guide.
The 🧾 beside a release number creates the sales order from it. It runs cERP's own Release Order, so cERP builds and prices the order, but you choose the lines in PM: the same filters as the release editor (including opening, building, floor and phase), a quantity for each line (full by default; lower it for a partial, untick to hold a line back), a new sales order or one of the contract's existing ones, and cERP's options. A preview by item category comes first. The lines you hold back keep their quantities in cERP, and the new order shows on Sales Orders and Deliveries right away. The Project Manager, Project Engineer, Commercial Project Manager, project admins, Logistics and administrators can do it.

The open sales orders cERP has raised from the releases: order, release, ship-to, dates, lines, quantities to ship. Tick orders and use the calendar button to shift several dates at once; a posted order shows as a link only.

What actually left the building: the posted sales shipments in cERP, with their lines and openings. A release's "Not Assigned" count on the Release Schedule is the lines no sales order or shipment carries yet.

Deliveries is the logistics view: every release, sales order and shipment as a dated delivery line, with counters for tentative, scheduled within 14 days, backordered, shipped and awaiting invoice. A sales order can ship in several postings: whatever a shipment leaves behind stays on the order as a backorder until a later shipment posts it. Such an order shows as Backordered here, Sales Orders shows each order’s Shipped and Remaining quantities and its shipments, Shipments says whether the order behind each one is complete, and the order’s Delivery task carries a Backorder tag, a percent shipped and what is still to come, staying In Progress until the last shipment posts. The Shipments / Deliveries switch at the left combines the orders and shipments going to one jobsite on one date by one shipment method into a single Delivery row; open it to see each shipment. The choice is shared with the Freight widget. Open in Delivery Planner jumps to the same job in the Delivery Planner, which owns delivery scheduling, truck routing and proof of delivery. The planner's Comsense shipments flow back into PM as Delivery tasks, and the project's External Users switch decides which outside contacts get delivery notifications.

The shop orders for the contract, open ones and posted ones in one list (a posted order shows its posted number with the original in parentheses), each opening to its lines and the openings they cover. The matching Shop Order tasks are what the plant sees on its task lists.

Shop orders follow their sales order. cERP carries a date change from a release to its lines and its sales orders, but it never re-dates the shop order that builds that order; it only raises an alert. PM closes that gap: when a sales order’s Requested Delivery Date moves by some number of days, every open shop order made for it moves its Start By and Due dates by the same number of days, so the shop’s lead time is kept. It happens whether the date was changed in PM (Sales Orders, Deliveries, a delivery task, or a release’s due date carrying its orders) or typed straight into cERP, where the next hourly pull picks it up. A shop order that someone already moved in cERP in the same hour, or whose task has its dates locked, is left alone and the reason is recorded in the project history. The SO Date column shows the sales order’s date beside the shop order’s own, in red when an open shop order is due after it, and the pencils on Start By and Due still set a shop order’s dates by hand.
The purchase orders raised for the job: vendor, ordered date, Promised Receipt Date (the pencil changes it in cERP), location, received and invoiced quantities, lines and amount, with receipts beneath each order. Two reports on the Reports page watch this table for you: promised receipt dates that are missing or past due, and material at risk of late delivery.

The page has two sections, each showing its count and amount on the header line. Purchase Orders from cERP (open by default) is the table above. Manual Purchase Orders (closed by default) holds purchase orders Purchasing placed outside cERP, usually before ePWS has pushed the job's material. It replaces the separate files and spreadsheets used until now, and it works even on a job with no cERP contract yet.
New purchase order opens a window laid out like cERP's Purchase Order screen. Pick the vendor by name or number and the buy-from address, phone, e-mail and contact fill in from cERP; you can still change them. Posting and Document Date start as today. Fill in Vendor Invoice No. and Vendor Order No., Expected and Promised Receipt Date, the Purchaser and the Location, plus notes that stay in PM. Lines pick items from cERP's item list, so they carry over without any reconciling. An item that is not on the list yet can still be saved: it is flagged, and Enter in cERP waits until the line is changed to a cERP item. Each manual PO gets a Purchase Order task, owned by its purchaser and due on its Promised Receipt Date.

When the order can go into cERP, use Enter in cERP from its row's ⋯ menu (every row action is in that menu, in the Actions column). PM creates the purchase order in cERP with everything mapped, then offers to open it there so you can finish it (assignments, release). The manual PO is archived with the new number and its task closes, so it is never counted in both sections; the cERP PO then shows in the upper section, marked with the MPO number. cERP accepts Non-Standard (NS…) items only from a contract's material, so any it refuses go over as comment lines saying what they were; add those from the contract material in cERP. If cERP refuses anything else, nothing is left behind in cERP and the manual PO stays open. Link to a cERP PO archives one that someone already entered in cERP by hand. Edit and Delete are in every open row's menu; Show archived lists the archived ones with their cERP number and a Restore button. After every cERP pull, PM checks what became of each archived one's cERP purchase order. Once it is fully invoiced, cERP closes it, so its status reads Posted in cERP and its link opens the posted invoices (or Received in cERP and the posted receipts, before the invoice). If cERP has no trace of it, its status reads Deleted in cERP in red. Purchasing and whoever entered it get one email; restore it to enter it again, or delete it. Purchasing (the department, or a Purchasing role on the project) and administrators can make changes; everyone else sees the buttons grayed out, with the reason.

Attachments. Keep the vendor's quote, the order confirmation or a drawing with the manual PO. Attachments in the row's ⋯ menu shows how many files it has (so does the Attachments column); click it to see them (click a name to open it), drag files onto the window or use Add files, and remove one with the trash can (click twice to confirm). The Edit window has the same Attachments area, so files can go in while the PO is being written; they are attached when you save. The files live on the manual PO's Purchase Order task, so they also appear on the project's Attachments tab, and they stay there after the PO is entered in cERP or deleted. The tab then marks them MPO-003 archived or MPO-003 deleted. Archived POs still take new files, for paperwork that arrives late. Each file added or removed is noted in the project's History, and the Excel export has an Attachments count. Files are up to 15 MB each, and the same Purchasing rule applies as for editing.

Purchase Order and Receiver documents. Purchase Order & Receiver… in a manual PO's ⋯ menu makes the two forms Purchasing sends out: the Purchase Order for the vendor and the Receiver for the warehouse taking the material in. Both are on the Millwork Brands letterhead and show the MPO number, the project, the vendor's address (From) and National Door & Trim at the plant's address (Ship to). The plant is the project's plant from Settings → Plants, and you can pick another. Each document has its own notes, one for each line and one for the whole document: the PO's line notes print under each line for the vendor, and the Receiver's print in red for the warehouse. Receiver notes start as the ETA from the Promised Receipt Date. The PO asks the vendor to send the order confirmation to you, the person who made it; Edit beside that line sends it to someone else instead, and is remembered for that PO. Create PO, Create Receiver or Create both attach the PDFs to the manual PO, so they also show on the Attachments tab; a new one replaces the last one of its kind. E-mail PO to vendor makes a fresh PO and sends it from the Project Manager mailbox to the vendor's address from cERP (which you can change), with you on CC and replies coming to you. Same Purchasing permission as editing; archived manual POs too.

The remaining pages are Schedule of Values (the material list by phase and category), Invoices (what has been billed and paid), Pricing (the estimate against the contract), Billing (the schedule of values as it is invoiced) and Revenue. They matter most to project management and finance; the same table tools apply.
Revenue is Finance’s monthly contract WIP and revenue recognition sheet, one row per month. It fills itself in from the billing periods saved on Billing: each month reads the approved AIA period (material still in storage and the total billed) and the month-end period (the cost forecast, the material installed and the contract value). When a billing period is saved, its Type is chosen (AIA, Month-end or Other); periods saved without a type are picked by their date. Tinted cells are the inputs; the finance roles that edit Billing can type over one, pick a different saved period for a month, and export the page to Excel with its formulas. Everyone else with access to the job can read it. A month with no month-end period saved yet shows its inputs only and is not counted. Once a month’s books are closed, its padlock locks it: the typed values and billing periods can no longer change. Months are locked in order, and only an application administrator or a person on the page’s Who can unlock list can unlock one to correct something.
Early every weekday morning (around 5:45 AM; administrators set the time) PM sends each person one email covering the projects that are In Progress: the tasks that are late or due within seven days, in one table per role (Assignee, Collaborator, Watcher) so your own work is never mixed with what you only watch, tasks that look finished but were not marked done, flagged reminders, change orders waiting for approval, and changes to the tasks you watch. You get a line for every task where you are the assignee, a collaborator or a watcher, which is why the people fields in section 2 matter. Immediate emails are rare on purpose: an assignment within fourteen days of its due date, a note that mentions you, a change on a task you watch. Everything else waits for the digest.
Contract reviewers also get a Contract Review section, whatever the project's status: each contract they still have to review, with the Contract - Internal Review start and due dates and a link to the review, plus every open flag addressed to them, until they click Done reviewing in the review window. The owner of Internal Review sees how many reviewers are done. It stops once the contract is Approved/Received or Internal Review is closed. The Contract Approval guide has the details.
Reports in the top bar opens the Reports page in its own tab. Each report lists who may open it and has an Excel download. Among them: the Active Job Board (the pipeline by stage and plant), the Installer, Field Superintendent and Project Management coverage trackers (who is on which job, month by month; a job with two Project Engineers shows under each of them, marked "shared with", and counts in full on each person's Workload card; dragging one engineer's bar swaps only that engineer, and the pencil lists every holder with + Add another), the Cash Flow Projection, Financial Snapshot and Comsense Invoice Review, the HubSpot Bid Metrics, Commercial Revenue Forecast and HubSpot Open Bid Forecast, the Release Schedule and purchase-order watch reports, the Manual Purchase Orders report, the Install Change Order Tracker, the Strategic Initiatives summary, and the Red Cedar unlinked list of sales orders with no PM task. Bid Metrics shows hit rate by estimator, project type, GC, Developer, Architect and state; a deal's Developer and Architect come from its PM project, else from HubSpot. Its By Month period shows bids per month against the monthly bid goal, Custom counts any date range, and Include rebids switches rebids out for new-bid counts. Its Qualifications section counts the deals entering Estimator Review, by week, month or year, against a weekly or monthly goal. It shows what became of them (quoted, won, lost or not pursued) and how many deals are waiting in Estimator Review now. It has its own Deal owner, Plant and Project Type filters. Every Bid Metrics filter list has All, Clear and Invert links: to see everyone but a few GCs, pick those few and click Invert. The HubSpot Bid Tracker is the estimators' calendar of bids by Bid Date, where a bid can be assigned to an ND&T Estimator. It also shows when people in the Preconstruction department are out: anything marked Out of Office on their Outlook calendars appears on its day with how long they are out (All day, Half day AM, or times such as 2:30–4:30 PM, never the subject). Above each week, labeled with its dates, is how many estimator-days are left after time out, beside the bids due that week. Assigning a bid to someone who is out on its Bid Date, or in the two business days before it, asks first. On the Installer coverage tracker, the Deal stages switches add the pipeline (LOI Received, Verbal Commitment, Expecting (75%) and 50%) to the won jobs, so whoever sends installer bids can see each installer's load and the jobs coming. Pipeline jobs are drawn hatched and marked with their stage. They count as bids, never against an installer's target or in its suggestions. You see the reports your department or name is on.

The Commercial Revenue Forecast (the HubSpot Bid Forecast until October 30, 2026) charts revenue and gross margin by month across three groups, each with its own button and a subtotal row under every plant: Open Bids and Won Bids from HubSpot, weighted by their stage's win %, and Active Jobs, every PM project at Contract Received - Active. For an active job the forecast is what is Left to Bill. Every started cERP job follows its release schedule, with nothing to switch on: a job joins as soon as it starts in cERP. It is recognized on ship: every month is its cost × the job's Line Value ÷ its planned cost, so what is left to forecast is Line Value less what has shipped or been installed (its left-to-invoice figure shows beside it). Material lands in the month its release is due to ship (the earliest open sales order's Shipment Date, else the release's Due Date; material on no release spreads evenly to the End Date), and installation runs level from this month to the end of its window, First Delivery through one month after the Last Scheduled Delivery. Both dates, and the job's margin, show PM's value in the forecast window and can be typed over there for the forecast alone. Open the arrow by the job's name for its Material and Installation rows. Change orders at Planning in cERP are left out until they are Unapproved or Approved. The months already gone show what shipped, shaded, on that job's row only and in no total. The Unreleased cost button lists, per cERP job, the cost on no release yet, with its lines and a CSV download: a punch list of what still needs a dated release. The forecast window shows the job's own curve month by month (shipped, invoiced, forecast, % of job) and the releases still to ship. On a job still riding out on Comsense, Left to Bill is the Balance To Invoice of its orders (the numbers in the project's Comsense field) on the latest Comsense Orders Analysis report imported into PM, spread evenly to the End Date. Comsense prints only open orders, so a Comsense job none of whose orders are on that report counts as finished, with nothing left to bill. One whose End Date has passed while the report still shows a balance stays in, flagged so the order can be closed out in Comsense or overridden. A job with nothing in either system yet follows its Project Type curve, like a won bid, unless its End Date passed more than 90 days ago: then it counts as finished, flagged so it can be closed in PM or linked to its order. Money that has no month left to go to sits in a Past End Date column until the End Date is fixed or someone overrides it. Such a job carries a red flag beside its name, and the Past End Date button under Active jobs in the filters lists just those jobs. Between the table and the Monthly Forecast, Show reconciliation opens a check of every cERP job: its Release Total (cost on releases), Negative Change Orders (material removed, which cERP cannot put on a release) and cERP's Master Total. Reconcile Total is Master Total − (Release Total + Negative Change Orders); a job that is not $0.00 is flagged, because its releases need correcting in cERP before its forecast months can be trusted. Click a job's Not on a Release amount to list the material list lines and openings behind it. A bid or job whose total comes to $0, such as a finished job, is left off the report. Below the plants, the Open Bids (all plants), Won Bids (all plants) and Active Jobs (all plants) rows open with a click onto each stage's subtotal across both plants (Hold through 50%, Expecting through LOI Received, and cERP jobs, Comsense jobs and Not started), and each of those opens onto its jobs from both plants, each named with its plant. The margin comes from the project's Settings, the first of: the Financials Current Margin (the typed value, or, when it is set to calculate from cERP, the margin from actuals so far), Detailed Margin, Estimated Margin, then the HubSpot margin. Margin Source says which one was used. The Gantt opens on Adjusted Total Revenue; switch to Total Gross Margin to see each subtotal and total with its margin % in a colored badge (red below 33%, yellow from 33%, green from 35% unless an admin changes the steps under Forecast Settings → Margin Badges). The Margin % button turns the badges off and on. Year-total columns have heavier borders and larger type. Each plant's Open Bids has a Stretch / Adjustment row, just above its first Deal Stage. It is calculated: open bids tend to start about half a year later than first forecast, so two-thirds of each month's Open Bids is taken out of that month and added back six months later (money that would land past the report's last month is left off). It counts in the plant's Open Bids subtotal, the plant total and the Overall Total, and a read-only Stretch / Adjustment (all plants) row under Open Bids (all plants) adds the plants together. The Total Gross Margin view does the same with the bids' gross margin. App admins, and the people an admin ticks under Forecast Settings → Stretch Editors, click the row's pencil to type over any month, then Save or Cancel. A blank month keeps its calculated amount, shown in gray; a typed month is bold and underlined, and only typed months stop following the bids. The row's Reset button removes the typed months, so the whole row is calculated again. An admin can change the two-thirds and the six months on the same Stretch Editors tab. The row shows how many months were typed, who saved last and when, and its clock icon opens the change history. The same people can add manual rows anywhere in the table, for an account PM has no jobs for, such as Red Cedar Homes under Lexington's Active Jobs. Click the + on any section heading (Open Bids, Won Bids or Active Jobs of a plant, or of all plants), then name the row and type its monthly revenue. You can also set an optional margin % for the Total Gross Margin view (blank uses the section's own margin) and a note that shows on hover. Fill right copies a month into every month after it. A manual row sits right under its section heading (in Open Bids, above the Stretch row) and counts in every total and the Excel download; an all-plants row counts only in the all-plants line and the Overall Total. Its pencil edits it, deletes it, or moves it to another section; its clock opens its history, and a warning appears when the current month is still blank.
The Strategic Initiatives report is the leadership summary of the 2027 Strategic Initiatives project, read live from it. Each initiative is a main task (type Main Initiative Task, tagged Initiative 1 through Initiative 8), and its card shows the owner (the assignee) and the Initiative Status color, with last month's color beside it when it changed. The milestones are the checklist items on the main task, and their share checked off fills the progress bar. The initiative's other tagged tasks (type Initiative Milestone) are counted beside it, with the next three due and anything blocked. Each owner has a monthly Initiative Update task, due the first Monday of each month (the next business day when the office is closed), whose description holds the four update questions. The owner answers in a note and marks it Done, and the card shows the latest answer. A card is flagged when an update is past due, or when none has been completed in 35 days. Only the project's people and administrators can open it.
The HubSpot Open Bid Forecast is still on the Reports page, just as it was before won bids and active jobs were added: the five open-bid stages only, one monthly spread curve for every deal, and a Gantt by Plant, then Deal Stage. The two reports share their win percentages. Each keeps its own spread curve, so changing one never moves the other.

The job's Project Manager, Brian Bennett, Cory Michaud and administrators can change an active job's forecast. Click the pencil or any month from this one on. The window shows the job's Project Type and its curve, its Start, First Delivery and End Dates, and its margin; those are changed in the project's Settings, not here. Left to Bill can be overridden: the system's figure stays on show beside it, and the months divide whichever one is in effect. Spread can switch the job from the system's spread (its cERP releases, the Comsense spread, or its own type's curve) to any Project Type's curve. Each month shows the system figure as an amount and as a % of Left to Bill. Type a forecast amount or a forecast %, and the other fills in to match; leave a month blank to keep the system figure. The arrow puts a month back, and Reset all puts the whole job back. A forecast that adds up to more than the system shows left to bill is allowed, but it is called out in red on the report and in the window as you type. Overridden months are outlined. Each change is written to the project's history.
The Comsense jobs' base comes from Comsense's Orders Analysis Report. Print it from Comsense as a PDF, then Import Orders Analysis on the line under the group buttons (administrators, Brian and Cory). Before anything is saved, PM checks that the orders add up to the report's Grand Total and shows each Comsense job's Left to Bill now and from the report. Where a project's Current Margin is set to calculate from actuals, the report's Curr. GM% is that actual. A newer import changes the system figures but keeps every override. The forecast window lists the job's orders with the previous import's Balance To Invoice beside each, and a job overridden before the latest import says so. Click Use the system figures there, or the arrow beside an overridden job's Left to Bill, to drop its overrides. The line turns yellow once the report is more than 14 days old. Orders not on an active job lists orders on the report that no Contract Received - Active project names. Link one to its project (PM suggests the job whose name matches, and adds the number to that project's Comsense field) or hide it if it is not a PM job. A job whose report Contract Amount is more than 5% off PM's is flagged. With Active Jobs on, the cERP jobs, Comsense jobs and Not started buttons show or hide each kind of job.


The Manual Purchase Orders report (Purchasing, Finance and Officers) lists every manual PO on every project, in two sections. Access to the report is the only gate, so it also covers projects you cannot open in PM, and their attachments open from the report. Open (expanded) flags a passed Promised Receipt Date and lines whose item is not in cERP's list yet. Archived (collapsed; click its header to open it) shows the cERP PO each one became, the cERP PO amount and the difference from the manual PO, in amber when they disagree. A fully posted PO's amount is what was invoiced, net of credit memos, and its link opens the posted invoices. One deleted in cERP is flagged in red. Both sections are grouped by project, with a subtotal per project and an overall total. The paperclip lists a PO's attachments and opens them, and the MPO number jumps to the project's Manual Purchase Orders section. Filters, saved column layouts and an Excel file with Open and Archived sheets work as on the other reports.

The Install Change Order Tracker replaces the Install team’s CO T&M Tracker workbook for Commercial projects that are completely on cERP: Install on, a cERP JOB contract, and no Comsense job. Projects that still involve Comsense are left out from the card’s editors window. Projects gives one line per project: the installer and its HubSpot status (anything other than Qualified is shaded), the PM, PE and Field Superintendent, T&M rates, and the installer contract. That covers the original value, sold and unsold change orders, the new contract value, cERP’s install contract value and the difference. The line also carries the workbook’s margins (pre-con margin, CO selling and cost, money gained) and the installer’s pay-application position. Unsold, Sold and All change orders list every project’s change orders, and the Installer Checklist tracks contract, T&M process, safety, COI, WC and AIA per installer.

Click a project to open its tracker. Change Orders holds one row per change order: status, sold, type, MBI and installer CO numbers, installer amount, customer sell and the gain. Every install change order in cERP appears there by itself, with cERP’s number, description and sell filled in. Contract & Totals holds the installer’s original contract value, labor rates and the AIA-style summary. Pay Applications records each of the installer’s pay applications with retainage, Installer Checklist holds one card per installer, and cERP shows the contract’s install lines. The Install department and application administrators edit, and every save lands in the project’s History.
The Comsense Invoice Review replaces Finance’s month-end invoice review workbook. Each morning the Comsense server’s 6:30 upload brings the last 13 months of invoices, and the report lists every one: Prior business day on top (yesterday, or Friday on a Monday), then the invoiced date range below with This month, Last month and Everything. Invoices that look odd carry a flag chip; hover it for the reason: a credit, a zero total with cost, a negative, low or high gross margin, or a due date that does not match the terms. Type a Note and tick Reviewed on any invoice; both are kept with the invoice and carried into the Excel download, which follows the workbook’s layout. Invoice #, Reviewed, Flags and Note stay pinned on the left while you scroll across. The envelope on the report’s card (on the Reports page) opens the email settings: the morning email (days, time and recipients; flagged invoices first) and can send a preview to you or send it now.

| Between | Into PM | Out of PM |
|---|---|---|
| HubSpot | New Commercial projects; fields, people and companies refreshed in early stages; every stage move; companies into the Developer, Architect, GC and Installer directories. | From Contract Received - Active: fields, people and company labels onto the deal, daily and from the Sync window. Never a new HubSpot company or user. |
| SupplyPro (Red Cedar) | Projects, lot tasks and their dates, every fifteen minutes. | Nothing. Date Lock is how you hold a date against the feed. |
| cERP | Openings, material, releases, sales orders, shipments, shop orders, purchase orders, invoices, hourly and nightly; Delivery, Shop Order, Purchase Order and Release tasks. | Release due dates, sales order dates, promised receipt dates, shop order dates; releases created and lines put on, between or off them; opening details (hand, heading, area, locations, sizes, keying); purchase orders created from manual purchase orders. |
| Delivery Planner | Comsense shipments as Delivery tasks; proof of delivery status. | The project's delivery notification recipients; the Open in Delivery Planner link. |